1. Blockage at the discharge port of the distribution valve
The discharge port is blocked, usually the pumping system is suddenly interrupted, and there is abnormal sound, the equipment has strong vibration, but there is no corresponding vibration in the pipeline.
Remedy: Pour cement slurry into the hopper, and start the pump repeatedly in forward and reverse directions to force the passage to open. If this method is not daring, you can only remove it manually, remove the connecting pipe, and remove the debris in the valve.

2. Blockage at the feed inlet
The feed port is blocked, usually the pumping action and hydraulic system are normal, there is no abnormal sound and vibration, there are large aggregates or agglomerates in the hopper, which are stuck or arched at the feed port.
Remedy: Run the pump in the reverse direction to destroy the agglomeration, return the concrete to the hopper and re-mix, and then pump forward. If it doesn't work, it needs to be cleaned up manually and eliminated.
3. The concrete pipeline is blocked
When the conveying pressure gradually increases, but the hopper level does not drop, the pipe outlet does not discharge, the pump vibrates, and the pipeline is also accompanied by strong vibration and displacement, it can be determined that the pipeline is blocked.
Judgment of blockage: blockage generally occurs in elbows, tapered pipes, and areas with vibration. At this time, you can use a small hammer to hit along the pipeline. The dull sound is blocked; the crisp sound is normal. With ears, rustling sounds are normal, and harsh sounds are blockages.

4. The pipe valve is blocked
The blockage at the pipe valve is gradually formed. The main reason is that after the concrete is pumped, it is not washed with high-pressure water in time, which causes the concrete to remain in the pipe, which gradually thickens over time, accumulates and solidifies, causing blockage. Remedy: After pumping concrete, be sure to flush the pump body and S pipe with high-pressure water. When the flushing is invalid, brazing can be used to remove the residue until it is completely clean.
Elimination method: When pipe blockage occurs, the method of repeating forward and reverse pumps should be adopted immediately, and the concrete at the outlet of the pump is gradually sucked back into the hopper for remixing and then transported. You can also use the method of hammering with a wooden hammer, combined with the forward and reverse pumps, to make it clear; when the above methods are invalid, it means that the blockage is serious.
After finding the blocked section, remove the pipe, use high-pressure air blowing or hammer hit or high-pressure water to wash, after thorough cleaning, connect the pipe to continue pumping concrete.

Are you looking for a reliable manufacturer of down home textile products?

We can quickly provide customers with market analysis, technical support and customized services.
Contact Person
Michael Liu
Name:
Michael Liu
Tel:

+0086-186-69798625

+0086-532-89659612

Email:
WhatsApp:
8618669798625
Address:
Office: 216# THE 308 STATE ROAD, CHENGYANG DISTRICT, QINGDAO SHANDONG,CHINA. Factory: No.413# Tieqishan Road, Yuhuangling Industrial Park, Chengyang District, Qingdao, China
follow us
Please send your message to us
*Email
Mobile Phone
*Title
*Content
Upload
  • Only supports .rar/.zip/.jpg/.png/.gif/.doc/.xls/.pdf, maximum 20MB.